Deferred Update Due Date plug-in properties
The Deferred Update Due Date plug-in updates the due dates of a running process or assignments within the process. This is run by SVService, and is useful if you are trying to update the due date for the current process being run, rather than an external process.
Value Pair |
Description |
assignmentid |
The identifier of the assignment whose due date should be changed. One of assignmentid or processid must be specified. |
date |
The absolute date to use in the update. If both date and timespan are specified, the date argument will be used. |
processid |
The identifier of the process whose due date should be changed. One of assignmentid or processid must be specified. |
timespan |
The timespan in .NET format to use in the update. If both date and timespan are specified, the date argument will be used. |
Examples
The following example shows how to update the process whose identifier is contained in the SharePoint field ProcessId with the date that is contained in the NewDate field.
- date - [NewDate]
- processid - [ProcessId]
The following example shows how to update the due date of current running process to 20 days later .
Processid – [$Process.Id]
Timespan - 20.00:00:00